Requisition Budget Check Link Is Enabled But Not Executing When Editing An Approved/valid REQ.

(Doc ID 2373594.1)

Last updated on MARCH 14, 2018

Applies to:

PeopleSoft Enterprise SCM eProcurement - Version 9.2 and later
Information in this document applies to any platform.

Symptoms

ENVIRONMENT:
-------------------
Test/Development environment:
Application Release: FSCM
PeopleTools Release:
Fixes/Bundle/Maintenace,Service Packs applied on to the environment you reported the issue:
Database (SQL Server / Oracle):
Platform with version (Windows/Unix):
Any customizations on the pages/processes related to this issue you reported:
Third Party Integration:

ISSUE:
--------
Requisition budget check link is enabled but not executing when editing an approved/valid REQ.

Actual Behavior:
---------------------
Requisition budget check link is enabled but not executing when editing an approved/valid REQ.

Steps:
-------
1. Using EProcurment Manage Requisitions, edit a requisition that is a status of Approved and a budget check of Valid.
2. Click OK to the Message: This requisition is approved. Editing this requisition may restart the approval process. (18036,6249).
3. Reduce the item quantity.
4. Click Save for Later.
5. Click OK to the Message: This action will restart the approval process. Click OK to continue or clock Cancel to go back. (18036, 12207).
6. Click the now enabled Check Budget hyperlink.
7. The Budget Status stays at Not Checked. You can tell budget check is not being executed as the processing circle is not displays at the top right of the page.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms