CONTRACTS ADDED TO REQUISITIONS DO NOT REMAIN AFTER SAVE

(Doc ID 2382405.1)

Last updated on APRIL 04, 2018

Applies to:

PeopleSoft Enterprise SCM eProcurement - Version 9.2 and later
Information in this document applies to any platform.

Symptoms

On : 9.2 version, Requisition Create

ACTUAL BEHAVIOR
---------------
Procurement Contract Issue

Prcourement contract re not staying on req line for special items on Procurement contract.

We are PS 9.2, Image : 18, tools : 8.55

Please review the attached document for details.

EXPECTED BEHAVIOR
-----------------------
Contract should remain on the line for special requests

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
REPLICATION STEPS
=================
1. find a general contract
2. create a epro requisition
3. add the contract to the req
4. save and submit
5. open the req and validate the contract is still visible
6. contract is missing.
 

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, special request items will not keep the contract price

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms