PC_POADJUST Abend at Step PC_POADJUST.QUANTITY.COND_1 (Action SQL) -- RC = 805

(Doc ID 2390514.1)

Last updated on APRIL 24, 2018

Applies to:

PeopleSoft Enterprise FIN Project Costing - Version 9.2 to 9.2 [Release 9]
Information in this document applies to any platform.

Symptoms

PC_POADJUST is abending with an unique constraint  at step PC_POADJUST.QUANTITY.COND_1 when having a voucher with Freight.


Steps:
1. Add a new project.
2. Create PO.
3. Drill down on the Schedule/Distribution icon for the PO line.
4. Update Distribution GL, Project & Activity created from step 1. Save
5. Dispatch PO.
6. Run PC_PO_TO_PC.
7. Dispatch PO.
8. Run PC_PO_TO_PC to bring PO to project costing.
9. COM row created.
10. Create a voucher by copying the PO.
11. Change unit price to $1,000.00 and add freight of $50.00. Save.
12. Post voucher.
13. Run PC_AP_TO_PC with the Application Options set to Detail.
14. Run PC_POADJUST.

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms