Symptoms

Updating multiple Work Orders with Task Actual Dates/Times on the Technician Workbench causes a performance issue.


The issue can be reproduced at will with the following steps:

1. Go to Technician Workbench.
2. Go to “Task Actual Dates/Times” tab.
3. Enter date and time on all Work Order Tasks in grid.
4. Save.