Goal

User is unable to reduce partially paid PO line to amount paid?

Steps
1) Go to Add/Update PO’s and click find an Existing Value  
2) PO: 0000nnnnnn
3) Select Header Details
4) Change Accounting Date to Current Date
5) Click the PO schedule
6) Select Price adjustment:
7) Change Price to the amount spent plus .01 to spend down the PO ( $5,200.01), then click OK.
8) Select Distribution/Chartfield
9) Change the open line to .01  and click ok
10) Press Save and the Matching message will appear:  

Error
Schedule has been matched. Cannot reduce price on matched schedule (10200,85)
 

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.