EPC: Total Distributed Budget Is Zero in the Budget Plan if the Project Is Not Active
(Doc ID 2731465.1)
Last updated on NOVEMBER 24, 2020
Applies to:
PeopleSoft Enterprise FIN Project Costing - Version 9.2 to 9.2 [Release 9]Information in this document applies to any platform.
Symptoms
Total Distributed Budget is displayed as zero in the Budget plan if the project is not active.
Steps to reproduce the issue:
1. Create a project in Pending status.
2. Create an activity.
3. Create a budget plan.
4. Add a budget item in the Budget Detail page and distribute the amount.
5. Click on Even Spread and then save.
6. Return to Budget Plan. Total distributed amount is zero.
If activating the project, the total distributed amount is reflected.
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
References |