E-UPG: Performance Problem with Upgrade Program AE_SYNCIDGEN (Doc ID 621225.1)

Last updated on JULY 20, 2015

Applies to:

PeopleSoft Enterprise PT PeopleTools - Version 8.40 to 8.53 [Release 8.4]
Information in this document applies to any platform.

This document was previously published as Customer Connection Solution 200759895




Goal

Upgrade program AE_SYNCIDGEN is running very slowly. In one situation, has run for 10 hours without finishing.
In the initial pass the process would run about 2 hours maximum, but in the most recent passes of Test the Move to Production, the process is taking 10 hours. There is nothing else on the server where the Upgrade is occurring.
Would like performance to be improved before the go live weekend.