PeopleSoft Enterprise Project Costing: Time Report cannot be saved - error "PC Business Unit - Project - Activity combination is not valid (13100,710)" (Doc ID 884135.1)

Last updated on SEPTEMBER 15, 2016

Applies to:

PeopleSoft Enterprise FIN Project Costing - Version 9 to 9 [Release 9]
Information in this document applies to any platform.
***Checked for relevance on 06-Nov-2013***

Symptoms

Enable Project Charging Level at Activity Costing Level '1'. Create a project and a WBS ID structure with parent and child activities.

Create a time report. Press Save For Later. The error is returned: "PC Business Unit - Project - Activity combination is not valid (13100,710)".

During the saving of the page, the trace shows that the system is looking at the view PS_PC_ACTEAM_TE_VW to do the validation. However, the view returns the parent activities, which is why the error is being presented.

The view selects activities with the field COSTING_ACT_SW = 'Y'. The parent activities all have the field COSTING_ACT_SW set to 'Y', however for the child activities the field COSTING_ACT_SW is set to 'N', which is why the system does not allow the time report to be saved.

Cause

Sign In with your My Oracle Support account