EPC8.9+: WORKFORCE_SYNC Not Sending Over CWR Rows With EMPL_RCD = '1' From HR 9.0 To FIN 8.9 (Doc ID 942980.1)

Last updated on SEPTEMBER 15, 2016

Applies to:

PeopleSoft Enterprise FIN Project Costing - Version 8.9 to 9 [Release 8.9 to 9]
Information in this document applies to any platform.

Symptoms

Create a Contingent Worker Instance for an employee in HR 9.0. The information will be sent over from HR 9.0 to FIN 8.9 using service operation WORKFORCE_SYNC.

In PS_JOB (HR 9.0) the employee will have two rows:

1st row with EMPL_RCD = '0' and PER_ORG = 'EMP'
2nd row with EMPL_RCD = '1' and PER_ORG = 'CWR'

However, in PS_JOB (FIN 8.9) the row with EMPL_RCD = '1' is not there. The XML message which is sent by HR does not contain any data.