No demand Can Be Found in the 'Material Plan Workbench' Page when the 'MRP Solver' Process (PL_RUN_MRP) Generates Purchasing Messages (Doc ID 968281.1)

Last updated on AUGUST 04, 2016

Applies to:

PeopleSoft Enterprise SCM Supply Planning - Version 8.8 SP1 to 9.1 [Release 8.8 to 9]
Information in this document applies to any platform.

Symptoms

When the 'MRP Solver' process (PL_RUN_MRP) is run (navigation: Supply Planning. Solve Plan, Initiate Material Solver) and it is generating Purchasing Messages, no demand can be found in the 'Material Plan Workbench' page (navigation: Supply Planning, Solve Plan, Material, Material Plan Workbench).

Cause