Cannot Run EIM "SBL-EIM-00206: Failed to run initial process." (Doc ID 747959.1)

Last updated on MARCH 02, 2017

Applies to:

Siebel Enterprise Integration Manager - Version 8.0.0.5 SIA [20420] and later
Information in this document applies to any platform.
""""Checked for relevance on 10-Nov-2014""""
""Checked for Relevance on 13-APR-2016""


Symptoms

Statement of what the issue is
Version: 8.0.0.5 SIA [20420]

When EIM task run, it is exiting with following error:

SBL-ADM-60070: Error reported on server 'usolsrvr' follows:
SBL-SVR-01042: Internal: Communication protocol error while instantiating new task SBL-EIM-00206: Failed to run initial process.
SBL-EIM-00206: Failed to run initial process.

Steps:

1. Prepare any EIM table for EIM load.
2. Create ifb file and add IGNORE BASE COLUMN parameter to ignore certain columns from populating:
3. Run EIM task.


Cause

Sign In with your My Oracle Support account