SuperCluster M6-32 - How to cleanly shutdown and startup an Oracle SuperCluster M6-32
(Doc ID 1674297.1)
Last updated on MARCH 31, 2022
Applies to:
Oracle SuperCluster M6-32 Hardware - Version All Versions to All Versions [Release All Releases]Oracle Solaris on SPARC (64-bit)
This document will address the various offered configurations of Oracle SuperCluster M6-32, if there are any variations approved as exceptions then the steps describes in this document may vary.
Goal
Describe the recommended procedure for cleanly powering down and powering up an Oracle SuperCluster M6-32
Solution
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Goal |
Solution |
Shutdown Procedures |
Obtain a list of all running zones |
Shutdown all non Oracle Database applications running on zones |
Login to each zone and cleanly shutdown crs and all DB resources with |
Obtain a list of all running LDoms from the primary (control LDom) in each PDom |
Stop the domains guest domains first |
Shutdown the CRS stack on all domains running Oracle CRS. |
Verify all oracle processes are stopped and if they are not remediate as necessary |
Check the Ldoms and zones depending on Oracle deployment that they are shutdown. |
Shutdown Exadata storage cell services and operating systems |
Shutdown the operating system of the control LDom |
Connect to the compute node ILOM and stop SYS |
Show and then set, if need be, the power switch settings so the M6-32 domains DO NOT power on automatically when the rack power is restored. The following show the settings that you want to reach. |
Shutdown the ZFS Storage Appliance |
The switches do not have specific power off instructions they will be powered off when power is removed from the rack. |
Flip the breakers on the PDUs to the off position. |
Startup Procedures |
Flip the breakers on all PDUs to the on position |
Verify and if necessary fix the partitioning on the IB Switches |
Startup the ZFS Storage Appliance |
Verify the startup of the Exadata storage cells |
Bring up the M6-32 domains |
Verify the system |
Restart all applicable applications and test. |