Goal
Provide follow-up reconfiguration steps to be performed after Infiniband (IB) switch replacement.
This document is intended to be used immediately after physical replacement steps have been completed, as detailed in the How to Replace documents. Also, the How to Prepare document must also have been followed prior, to prepare the plan for this stage. Refer to: Infiniband Switch Replacement – Overview and guide to key articles (Doc ID 2125242.1)
Note: For IB switches within an exalogic system, use Doc ID 2218689.1 instead of this document
Solution
Sign In with your My Oracle Support account |
|
Don't have a My Oracle Support account? Click to get started |
My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms