How To Change The Enterprise Manager Harvester Job RunTime Schedule (Doc ID 1325594.1)

Last updated on APRIL 29, 2017

Applies to:

Oracle Configuration Manager - Version 10.3.4.0.0 to 12.1.2.0.2 [Release 10.3 to 12]
Information in this document applies to any platform.

Goal

In some cases, there will be a need to change the Grid Control Harvester (GCHarvester) job schedule. 
Out of the box, the job is scheduled to run at 2:00am local time. 
However, the user has the ability to customize this run time schedule.
 

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms