Refresh to Essbase appears to Hang or not complete

(Doc ID 2064409.1)

Last updated on MARCH 13, 2017

Applies to:

Hyperion Planning - Version and later
Information in this document applies to any platform.


Refresh from Planning to Essbase does not complete.  Services seem to hang.  Essbase application appears to use a lot of memory on the essbase server (esssrv) or it stops responding:
Network error: Timed out before receiving all data



 Planning refresh occurs that triggers a restructure of a database (plan type) in Essbase