E1: 30: 31: 34: P00071 Shop Floor Calendar Setup and Use (Doc ID 1129994.1)

Last updated on JUNE 30, 2023

Applies to:

JD Edwards EnterpriseOne Requirements Planning - Version XE and later
JD Edwards EnterpriseOne Shop Floor Control - Version XE and later
JD Edwards EnterpriseOne Product Data Management - Version XE and later
Information in this document applies to any platform.

Purpose

Overview

The Shop Floor Calendar (P00071) program is used to determine the Work Day Calendar on the manufacturing shop floor and in material scheduling and planning.  It is required setup in system codes 30, 31, 33, 34.  It is used in distribution programs such as Sales Order entry and blanket Order Release and is used in Service and Warranty programs.  From menu G3041 or G3141, select Shop Floor Calendar (SFC) to define the work days, shut down, or holidays by month and year for each manufacturing branch in the system and for all shifts.  Shop Floor Calendar records are stored in the F0007 file and uses the V0007A business view.  Branch plant 'ALL' is a hard coded value to define a generic branch calendar but is not added to the Business Unit Master table (F0006).  The system uses this calendar to determine manufacturing schedules and back scheduling of work orders.  

The calendar can also be defined by shift. The system uses these shift calendars for line scheduling and sequencing by shift in repetitive manufacturing.  Shift Calendars are used in resource requirements planning but shift calendars are not used for Distribution Requirements Planning (DRP), Master Production Scheduling (MPS), or Material Requirements Planning (MRP).

Setup a Shop Floor Calendar as a prerequisite to Sales Orders, Blanket Order Release. Resource Units, MRP/RRP, Periods of Supply (POS) item entry, Equipment and Service work orders, and SWM cases, as well as the manufacturing work orders and back scheduling.

A Work Center Calendar or Named Calendar can be created for a special use or for use in repetitive manufacturing.  Like shift calendars, named calendars are not used for DRP, MPS, or MRP.  See Doc ID 631138.1 - E1: 30/31: P00071 Setup and Use of Named Calendars.

Details

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Purpose
 Overview
Details
 Setup of the Shop Floor Calendar
 Branch/Plant (MMCU) or (MCU)
 Calendar Year and Calendar Month
 Calendar Type (WDCT) and Calendar Name (WDCK) (optional)
 Resource Requirements
 Shop Floor and Material Planning (MRP)
 Frequently Asked Questions
 Question 1.  When adding a new calendar record, Century field on Workday Calendar Revisions form shows Blank. Unable to modify this Calendar due to Error 'Action Invalid'.
 Question 2:  How can we get MRP to consider Saturday working only for two work centers without having Saturday defined as working for the entire Branch?
 Question 3:  Opening P00071- Work with Workday Calendar, Error: 'File can not be accessed'.  Solution offered as Change IBM security or authority using the IBM EDTOBJAUT command. What is the cause of the error?
 Question 4:  R3483 running in Parallel mode fails with no error messages, could this be related to a calendar issue?
References