E1: 30A: 31A: Running Manufacturing Costing and Accounting Programs While Running Shop Floor 24/7 (R30812/R30835/R31802A/R31804) (Doc ID 1374908.1)

Last updated on OCTOBER 10, 2023

Applies to:

JD Edwards EnterpriseOne Shop Floor Control - Version XE and later
JD Edwards EnterpriseOne Product Data Management - Version XE and later
Information in this document applies to any platform.

Goal

Explain the order in which manufacturing jobs Frozen Cost Update, WIP Revaluation, and other manufacturing accounting jobs are run, and minimize downtime for running these jobs.

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
Solution
 Frozen Update (R30835) and WIP Revaluation (R30837) should not be run when the shop floor is in operation
 Never run Frozen Cost Update (R30835) with Open Unaccounted units
 Never run Manufacturing Accounting (R31802A) and WIP Reval (R30837) at the same time
 Never run R30837 and R31410 at the same time
 Inbound Super Backflush Processor (R31123Z1I) and Manufacturing Accounting (R31802A)