My Oracle Support Banner

E1: 34: MRP Planning Incorrect Transfer Order for P3403T Percent To Fill And AVLC=1 Used In Combination (R3483) (Doc ID 2937019.1)

Last updated on APRIL 02, 2024

Applies to:

JD Edwards EnterpriseOne Requirements Planning - Version 9.2 and later
Information in this document applies to any platform.

Symptoms

When the branch relationship record is set to non-zero value, such as 100 percent, in combination with the availability check flag (AVLC=1) enabled, the supply plant quantity on hand, less than the percent to fill quantity, gets a planned transfer order for the partial percent to fill. The next run will suggest a cancel message for the firm order that is for less than the percent to fill and a net new planned order for the partial requirement.

Steps:

  1. Setup a P41026 multiple plant planning item with a P3403T branch relationship record with both a non-zero Percent to Fill and with a Availability check flag enabled, AVLC = 1.
  2. Create a demand quantity in the demand plant greater than the supply plant on hand, considering the percent to fill.
  3. Run Multi-plant planning R3483 and review P3411 detail messages and the P3413 time series.
  4. From P3411, firm the planned transfer order message and firm the planned OP supply message, and rerun R3483 MRP.
  5. Review P3413 Time Series and P3411 for incorrect planning or incorrect messages.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.