P3411 ST/OT Scheduled Pick Date (PDDJ) Does Not Correspond To Start Date Given By MRP
(Doc ID 2964929.1)
Last updated on JULY 31, 2023
Applies to:
JD Edwards EnterpriseOne Requirements Planning - Version 9.2 and laterInformation in this document applies to any platform.
Symptoms
Work With Detail Messages P3411 is not taking into consideration the Transfer Leadtime defined in B/P Relationship – P3403T to calculate the scheduled pick date of the ST order if the Profile Processing = 1 is enabled in P4210 called version, but the R40400 specific version: Delivery Date = blank (not activated).
- Create an item in P4101, P41026 (stock item), Branch 30 ships to branch 20.
- P3403T Br Pl relationship, branch 30 supplies branch 20, set 1 day as Transfer leadtime.
- In Delivery Date Profiles P40309, set 7 days for item and branch 30.
- In P3411, POs versions, set a specific version of P4210 for ST/OT (copy the standard ZJDE0007). POs for the specific version of P4210 that is called from P3411, tab 9 Versions, set a specific version for R40400. Tab 10 Preferences: 1. Preference Profile Processing = 1 = Activate preference processing POs for R40400 specific version: Delivery Date = blank (not activated)
- P3411, create an Order message from an OT in branch 20 (demand) with Request date = 30 June. Open the record and process it.
- See the OT and get the corresponding ST.
- In P4210, check the dates:
requested 30 June
sched pick 30 June
promised ship 30 June
promised delivery 30 June
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
References |