Symptoms

Set-up Work Order Activity Rules (P4826) and ensure they are activated in the Manufacturing Constants (P3009). In the ETO Project Workbench Edit Tasks (P31P001) input a status 15 on a work order which is at a status 45. Select Save and Continue and received the error “Status Not in Status Flow”.  With out clearing the error, entered status 15 again, and again select Save and Continue. The status is updated to status 15 but this status is not valid in the Work Order Activity Rules statuses.

Steps To Duplicate:
1.  Ensure the P3009 Manufacturing Constants has the WO Activity Rules checkbox checked
2.  Check the P4826 Work Order Activity Rules and check the status flow
3.  On P31P001 ETO Project, change the status of a Work Order (type WO) to a non-valid status
4.  Receive the Status not in Status Flow error
5.  Overwrite the status to the same status number and tab out, and the error is cleared.  Expecting the error to remain because the status is not in the status flow.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.