E1: 31: Changing WO Requested Date in P48013 - Manufacturing Work Order Processing Leads to Related Outside Operation Purchase Order' Ordered Quantity, Unit Cost and Extended Cost Fields To Be Cleared
(Doc ID 3022056.1)
Last updated on JUNE 03, 2024
Applies to:
JD Edwards EnterpriseOne Shop Floor Control - Version 9.2 and laterInformation in this document applies to any platform.
Symptoms
For a WO with an outside operation step, when changing the Requested Date in P48013 - Work With Manufacturing Work Orders the system changes the OP Order Ordered Quantity and clears the Outside Operation Purchase Order Unit and Extended costs.
Steps:
- In P48013 have a WO with an outside OP step with a requested date 2 weeks in the future.
- In P4310, check the unit cost in the purchase order for the outside OP, enter a manual value (10 USD).
- In P48013 change the requested date to be 4 weeks into the future (or any other date different from the previous 2 weeks value).
- In P4310 for the outside operation OP notice the former unit cost is being changed (cleared).
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
References |