E1: 51: Change Request Entry (P5310) Is Not Allowing Subledger X To Have A Left Justification (Doc ID 3050629.1)

Last updated on SEPTEMBER 30, 2024

Applies to:

JD Edwards EnterpriseOne Project Costing - Version 9.2 and later
Information in this document applies to any platform.

Symptoms

 When entering a change request in P5310 - Change Request Entry, the system is not allowing subledger X to have a left justification.

Steps:

1. In P5310 enter a change request for subledger X.
2. See that the system allows to have right justification.

Cause