E1: 34: R3482/R3483 Basics of MRP Dates and Leadtimes (Doc ID 660707.1)

Last updated on APRIL 04, 2024

Applies to:

JD Edwards EnterpriseOne Requirements Planning - Version XE and later
Information in this document applies to any platform.

Purpose

The following document contains detailed information on commonly asked questions and will provide answers to questions on how MRP uses dates, lead times and how you can set up dates to fit your business needs.

Overview

MRP plans for parent and component supply using lead times (fixed or variable), transfer lead times (P3403T), and is influenced by lead or lag times (P3002) or defined freeze fences (P41026).

Users must be aware that MRP and the Supply and Demand (S&D) Inquiry (P4021) are different.  MRP provides static data tied to the last MRP generation date, and displays both adjusted (quantity if MRP messages are processed) and unadjusted values (no MRP messages processed).  S&D Inquiry will only display unadjusted values, so S&D users must also view the MRP Message Details (P3411) to view what MRP is recommending for new dates or quantities.

Details

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Purpose
 Overview
Details
 Dates Utilized by MRP Processing
 Definitions
 Leadtimes
 Transit leadtime
 Functionality
 Determining Component Stock Dates
 Transfer Orders
 Leadtime Offset
 Frozen Orders
 Safety Stock
 Common Error or Warning Messages
 Date Generation Failed Error
 Start Date > Calculated Start Date Warning
 Enhancement Requests