Goal

As of 11-2020, the latest release of WebCenter Content is 12.2.1.4.0.

This Note will provide example steps to upgrade a WebCenter Content server 11g to version 12.2.1.4.0. 

If you are upgrading from a previous version of WCC 12c, then use Note 2309958.1

 

Note: This will cover only the WCC Content Server, Inbound Refinery, and URM domains.  Not domains that also have other managed servers in them such as IPM, WebCenter Portal, or Capture.

However, in a multi-application domain, these upgrade steps are essentially the same. In addition to installing the WCC media, the media for the other applications are also required to be installed as part of step F.

 

Refer to the online documentation below for more information about upgrading URM.

Upgrading Oracle Universal Records Management from 11g to 12c

 

How long will this take?

The amount of time this takes is subjective to the environment such as:

1. Upgrading older 11g to 11.1.1.9

2. If this a cluster domain, then more time is needed for each additional node.

3. How much content is in the UCM repository.  For example, the readiness check will take longer for larger repositories.

4. Number of files in the domain folder.  For example, if the vault and weblayout are inside the domain folder, then this can add considerable amount of time.  Please see below KM note for details.

Reconfigure Script Hangs While Processing the Content Server Folders (Doc ID 2289214.1)

 

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
 How long will this take?
Solution
 Important Notes
 Platform requirements
 What will be retained and what will be changed
 STEPS
 A. Prior to upgrading 11g to 12c, upgrade the 11g to 11.1.1.9
 B. Disabling Obsolete Components Before Upgrade
 C. Disable custom components
 D. Install the latest Java JDK 1.8
 E. Install Weblogic 12c
 F. Install the WCC 12.2.1.4.0
 G. Download and apply the latest bundle patches
 H. Create the new required database schemas
 I. Run the Readiness Check for WCC Schema Upgrade and WCC Configuration Upgrade
 J. Upgrade the WebCenter Content database schemas
 K. Modify the 11g domain to 12.2.1.4.0 standards
 L. Set the WCC binaries to the new 12c Oracle_Home
 M. Check for the 12c middleware parameter paths
 N. Restart the Admin Server and Managed Servers
 O. The previous 11g files and directories can now be removed
 P. Re-enable custom components
 Q. Additional steps when the domain is clustered
References