Is It Possible For ASCP To Aggregate At The Beginning Of Days, Weeks, & Periods When Planning For Supplies?
(Doc ID 1062511.1)
Last updated on SEPTEMBER 09, 2023
Applies to:
Oracle Advanced Supply Chain Planning - Version 11.5.10 and laterInformation in this document applies to any platform.
Form:MSCFNSCW.FMB - Planner Workbench
Goal
One of the plan options is aggregation, which has 3 selections; Day, Week & Period. We would like to use more weekly aggregation. However, for weekly aggregation all supplies are planned on the last day of the week. We would like to have it aggregated on the first day of the week. Is there a way to set which day of the week in which the requirements are aggregated?
Solution
To view full details, sign in with your My Oracle Support account. |
|