Stopping an Engineer in ORS Causes All Jobs Allocated To The Resource To Be Deleted Due To Archive Stop Status List Settings (Doc ID 1266205.1)

Last updated on OCTOBER 26, 2011

Applies to:

Oracle Real-Time Scheduler - Version: 1.12.0 to 1.13.2 - Release: 1.12 to
This problem can occur on any platform.

Symptoms

The user opened the Driver Form in the Resource Manager Client and set a Finish Date.  This caused all future shifts, scheduled after the finish date, to be deleted.  Any jobs allocated to the resource on a shift were also deleted.

Users should expect jobs to be reassigned to alternate engineers when the original engineer's finish date is set.  Jobs should not be deleted.

Cause