Unexpected Planned Order behavior and/or past due Purchase Orders scheduled earlier even when on-hand is available (Doc ID 2339805.1)

Last updated on DECEMBER 15, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 11.5.10.2 and later
Information in this document applies to any platform.

Symptoms

In a 11.5.10.2 Instance or higher:
 
After running an Unconstrained ASCP Plan, one or more of the following behaviors are observed when reviewing the plan output:

- ASCP is scheduling a planned order well before the demand date that will consume it, and recommends a quantity that exceeds the demand
- Past due Purchase Orders are seen moved up to the plan run date and are pegged to the early demand even though there is enough on-hand to cover it
- Purchase Order partially pegs to excess while a new planned order is generated
- ASCP is suggesting planned orders in some time buckets when there is no Demand
- ASCP Plan is not considering the scheduled PO receipts that are due today, instead to meet the demand that is in the current bucket, it is creating a fresh Planned Order with an immediate need-by date.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.