Order is Provisioned On the Wrong NE And Stuck In 103 State On the ASDL Response In the SARM Server
(Doc ID 2495939.1)
Last updated on APRIL 25, 2024
Applies to:
Oracle Communications ASAP - Version 7.0.0 and laterInformation in this document applies to any platform.
Symptoms
- ASDL was completed on the wrong Network Element
- ASDL response is stuck in SARM and the WorkOrdser was staying in 103 state
- After restarting NEP the WO state was changed to 104 (Completed successfully)
- "Ignore ASDL Remove" message appeared in SARM diag file as below:
SARM Diag:
Changes
Cause