My Oracle Support Banner

PCONDES Task Is Not Assigning The Correct Network System On The Physical Connection VCONDES Failing (Doc ID 2677027.1)

Last updated on MARCH 23, 2021

Applies to:

Oracle Communications MetaSolv Solution - Version 6.0.15 and later
Information in this document applies to any platform.

Symptoms

On : 6.0.15.928.B24 version, Work Management

MSS 6.0 BEHAVIOR
=============

PCONDES task is not assigning the correct network system on the physical connection which is causing VCONDES task to fail in MetaSolv when picking a device for an order.  
 

EXPECTED BEHAVIOR
=============
PCONDES should pick the correct Network System so the VCONDES task could complete properly.

STEPS
=====
Processing PCONDES task and then the VCONDES task is generating the problem.

Provisioning process is as following:
- Dedicated Plant exists at address or is created for address by the PLNTDSGN task
- PCONDES applies dedicated plant to design automatically and selects the element based off the applied Dedicated Plant
- Element appears to be in two Network Systems (but really exists only in one)
- Incorrect Network System is chosen for the physical connection
- VCONDES attempts automation but cannot find valid paths from device in the selected Network System.



BUSINESS IMPACT
==============
PCONDES and VCONDES tasks need to be manually processed.


.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.