Usage Not Exporting When Copying Activity Usage Spreadsheet to Excel
(Doc ID 2758325.1)
Last updated on MARCH 10, 2023
Applies to:
Primavera P6 Professional Project Management - Version 17.12.0.0 and laterPrimavera P6 Enterprise Project Portfolio Management Cloud Service - Version 17.12.0.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 17.12.0.0 and later
Information in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
When copy and pasting the Activity Usage Spreadsheet to Excel, the timescale starts in December 1999 and no usage data is copied over.
EXPECTED BEHAVIOR
Expect data from Activity Usage Spreadsheet to copy over.
STEPS
The issue can be reproduced at will with the following steps:
- Log into P6 Pro.
- Open project.
- View Activity Usage Spreadsheet.
- Select all elements by hitting Ctrl+A.
- Copy all elements by hitting Ctrl+C.
- Paste to Excel. Timescale will start in Dec 1999 and usage data is not exported.
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |