ASCP Not Recommending Planned Orders For Non Standard Jobs Without Assembly
(Doc ID 2770805.1)
Last updated on JANUARY 18, 2023
Applies to:
Oracle Advanced Supply Chain Planning - Version 12.1.3 to 12.1.3.9.2 [Release 12.1]Information in this document applies to any platform.
Symptoms
On : 12.1.3 version, Memory Based Planner
ACTUAL BEHAVIOR
---------------
User is running Constrained EDD without DS plan, ASCP is not suggesting planned orders when there is no onhand for the non standard jobs if it does not have an assembly
EXPECTED BEHAVIOR
-----------------------
System should suggest the planned order for the non standard jobs
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Log into ASCP Responsibility
2. Run the Plan
3. Review the plan output
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |