Maintain Baselines Intermittently Creates Corrupted Baselines (Doc ID 2788841.1)

Last updated on MARCH 20, 2024

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 20.12.3.0 to 20.12.6.0 [Release 20.12]
Information in this document applies to any platform.

Symptoms

DESCRIPTION OF PROBLEM:
Intermittently, project baselines created using the maintain baselines feature are corrupted. They show a blank description and the BL dates are not created.

STEPS TO REPRODUCE:
1. Login to P6 Professional
2. Open a project.
3. Go to 'Project > Maintain Baselines'.
4. Choose 'Add' then 'Save a copy of the current project as a new baseline'.
5. Allow the baseline job to be processed by P6 Services.

The following error is thrown in the P6 Web\P6 Services logs.

com.microsoft.sqlserver.jdbc.SQLServerException: Transaction (Process ID nn) was deadlocked on lock resources with another process and has been chosen as the deadlock victim. Rerun the transaction.

NOTE: This issue is specific to Microsoft SQL Server databases and cannot be reproduced 100% of the time.

EXPECTED OUTCOME:
Corrupted baselines to not be created.

POTENTIAL WORKAROUNDS:
Delete the corrupted baseline then recreate it.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.