Selecting a Project to Convert as a Baseline Defaults to the Top EPS Node, Not the EPS Node Where the Project Is Located
(Doc ID 2795827.1)
Last updated on APRIL 04, 2023
Applies to:
Primavera P6 Professional Project Management - Version 18.8.20.0 to 18.8.24.0 [Release 18.8]Information in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
When attempting to reattach a baseline, the top EPS node is selected for the baseline project to copy, instead of remaining in the EPS node where the opened project resides.
EXPECTED BEHAVIOR
The highlight/selection should stay in the EPS node containing the opened project, as was the behavior in version 18.8.19 and earlier.
The issue can be reproduced at will with the following steps:
- Open a project.
- Highlight the project to be attached as a baseline to the open project.
- Select Project > Maintain Baselines from the menu, then click Add.
- Click Convert another project to a new baseline of the current project.
- Observe the reported behavior.