Operating a Device in Study Mode Does not Affect Network Energization the Same as Operating the Device in Real Time
(Doc ID 2851425.1)
Last updated on FEBRUARY 25, 2022
Applies to:
Oracle Utilities Network Management System - Version 2.3.0.2.0 to 2.5.0.1.0 [Release 2.3 to 2.5]Oracle Network Management for Utilities - DMS - Version 2.3.0.1.0 to 2.5.0.0.0 [Release 2.3 to 2.5]
Information in this document applies to any platform.
Symptoms
On : 2.3.0.2.0 version, Web Workspace
An operator reset their study session to real time and executed a switch plan in study mode.
The operator then executed that same sheet in real time.
The network energization did not match.
The conductor and device states in study mode were incorrect.
EXPECTED BEHAVIOR
-----------------------
The viewer should always be showing the correct conductor statuses
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
Fix Description |
Migration |
References |