'Ending With Activity' Selection for 'Calculate Multiple Float Paths' Is Retained after Changing the Default Project (Doc ID 2878942.1)

Last updated on AUGUST 01, 2022

Applies to:

Primavera P6 Professional Project Management - Version 20.12 to 21.12.6.0 [Release 20.12 to 21.12]
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 20.12 to 21.12.6.0 [Release 20.12 to 21.12]
Primavera P6 Enterprise Project Portfolio Management - Version 20.12 to 21.12.6.0 [Release 20.12 to 21.12]
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 22.1 to 22.7 [Release 22.1 to 22.7]
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR

In P6 Professional Tools > Schedule > Options > Advanced Scheduling Options > Calculate multiple float paths, the ...Ending With Activity selection is retained after changing the default project.

EXPECTED BEHAVIOR

The ...Ending With Activity selection should be removed when the default project is changed.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.