Baseline Data Does Not Populate after Refreshing Data via Alt+Shift+F5
(Doc ID 2879163.1)
Last updated on NOVEMBER 18, 2022
Applies to:
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 18.8 to 22.8 [Release 18.8 to 22.8]Primavera P6 Enterprise Project Portfolio Management - Version 18.8 to 21.12.8.0 [Release 18.8 to 21.12]
Primavera P6 Professional Project Management - Version 18.8 to 21.12.8.0 [Release 18.8 to 21.12]
Information in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
After running a global change, the 'Variance - BL Project Start Date' is not populated until the Activities page is manually refreshed.
EXPECTED BEHAVIOR
Expect data to be populated dynamically.
The issue can be reproduced at will with the following steps:
- In P6 Professional, open a project.
- Add columns for BL Project Start, Variance - BL Project Start Date to activity layout.
- Run a global change (e.g. Populating an activity code with data based on date criteria).
- After global change has been run and changes committed, refresh page by using ALT+SHIFT+F5.
- Data that was previously populated in BL Project Start, Variance - BL Project Start Date columns is now missing.
Changes
Cause