Using an example that exists in the demo data, there is MC Type "Electric Channel Statistics - Same Month Last Year" which has the following parameters:

Period End Lag Days - 365
Period Start Lag Days - 395
Current date = 5/18/2022

Due to the help text regarding this example, we used to expect the following range
Expected end date is 5/18/2022 - 365 days = 5/18/2021
Expected start date is 5/18/2022 - 395 days = 4/18/2021


However, when the statistics are calculated, the actual end date is 5/18/2021 but the actual start date seems to be calculated by taking the calculated end date
and subtracting the Period Start Lag Days parameter:  5/18/2021 - 395 = 4/18/2020.

Then the statistics are calculated for 13 full months:  04/18/2020 - 05/18/2021.

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.