P6 Professional Project Hangs During XER Import
(Doc ID 2895834.1)
Last updated on MARCH 01, 2024
Applies to:
Primavera P6 Enterprise Project Portfolio Management - Version 19.12 and laterPrimavera P6 Professional Project Management - Version 19.12 and later
Information in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
When importing a large schedule, in the format of .XER, the application freezes indefinitely.
EXPECTED BEHAVIOR
The import process should complete within a reasonable amount of time.
The issue can be reproduced at will with the following steps:
- Launch P6 Professional.
- Import the XER.
- Observe the application freezes and the XER import does not complete.
Changes
Cause