The Global Calendar Is Modified When Importing the Project Calendars That Are Linked to the Global Calendars.
(Doc ID 2924973.1)
Last updated on MAY 02, 2024
Applies to:
Primavera P6 Enterprise Project Portfolio Management - Version 17.12.10.0 and laterInformation in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
---------------
While exporting the project from P6 EPPM, includes the calendar in the "Project Calendar Dictionary" and try to import it to SQLite database when using XML format: any calendar at "Project Dictionary Calendar" is automatically linked to the Default Global Calendar at option (Inherit holidays and exceptions from Global Calendar), which affects the project dates.
EXPECTED BEHAVIOR
-----------------------
Import correctly the project calendar
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
- Open the P6 Professional
- File import Project XML
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |