My Oracle Support Banner

Calendar Workweek and Time Period Windows Do Not Show All Data (Doc ID 2941638.1)

Last updated on APRIL 17, 2023

Applies to:

Primavera P6 Professional Project Management - Version 22.12.1.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR

When trying to view Calendar Workweek or Time Periods in Enterprise > Calendars > Modify in P6 Pro, the whole screen cannot be viewed to change the hours.


EXPECTED BEHAVIOR

Calendar Workweek and Time Period windows should fit the window size properly and all information should be viewable.


STEPS TO REPRODUCE

The issue can be reproduced at will with the following steps:

  1. Login to P6 Pro.
  2. Go to Enterprise > Calendars.
  3. Select a calendar.
  4. Click Modify.
    1. Select Total work hours/day.
      1. Select Workweek: Notice Calendar Weekly Hours window does not fit properly, therefore does not show all data:
      2. Select Time Periods: Notice Hours Per Time Period window does not fit properly:
    2. Select Detailed work hour/day:

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.