Symptoms
ACTUAL BEHAVIOR
When trying to view Calendar Workweek or Time Periods in Enterprise > Calendars > Modify in P6 Pro, the whole screen cannot be viewed to change the hours.
EXPECTED BEHAVIOR
Calendar Workweek and Time Period windows should fit the window size properly and all information should be viewable.
STEPS TO REPRODUCE
The issue can be reproduced at will with the following steps:
- Login to P6 Pro.
- Go to Enterprise > Calendars.
- Select a calendar.
- Click Modify.
- Select Total work hours/day.
- Select Workweek: Notice Calendar Weekly Hours window does not fit properly, therefore does not show all data:
- Select Time Periods: Notice Hours Per Time Period window does not fit properly:
- Select Detailed work hour/day:
- Select Total work hours/day.
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |