Gantt Chart Bars Are Not Adhering to Row Settings (Doc ID 2943903.1)

Last updated on AUGUST 09, 2024

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 19.12.2.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR

In P6 Pro, there are four bars showing in the Gantt Chart: Yellow, White, Green and Red.
The Yellow bar is set to Row 1 and the other three bars, White, Green and Red, are set to Row 3 and all Rows are behaving as expected.
After changing the Yellow bar to Row 3, from Row 1, the other three bars move to Row 1.


EXPECTED BEHAVIOR

Changing the Yellow bar to Row 3 should not move the other three bars to Row 1.


STEPS TO REPRODUCE

The issue can be reproduced at will with the following steps:

  1. Login to P6 Pro.
  2. Open Project.
  3. Notice bars look correct:
    1. Yellow Bar is on Row 1.
    2. White bar is on Row 3.
    3. Green bar is on Row 3.
    4. Red bar is on Row 3.
  4. Right click on Gantt Chart and select Bars.
  5. Highlight the Yellow bar and change to Row 3.
  6. Click Apply.
  7. Notice White, Green, and Red bars all move to Row 1.

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!