P6 Professional "Date Added" In Maintain Baseline Dialogue Shows Wrong Date
(Doc ID 2944235.1)
Last updated on APRIL 24, 2023
Applies to:
Primavera P6 Enterprise Project Portfolio Management - Version 21.12.9.0 and laterPrimavera P6 Enterprise Project Portfolio Management Cloud Service - Version 21.12.9.0 and later
Information in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
---------------
When looking at the Column “Date Added” in the Maintain Baseline dialog, the date does not match the date when the baseline was added.
Instead, it is showing the date when the project was created.
EXPECTED BEHAVIOR
-----------------------
When looking at the Column “Date Added” in the Maintain Baseline dialog, the date should match the date when the baseline was added.
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Open a project in P6 Professional
2. Go to Project / Maintain Baselines
3. Add a baseline using either method (copy of project / convert another project)
4. Note the Date Added of the newly added baseline
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
References |