Advanced Supply Chain Planning Is Not Considering Substitutue Components
(Doc ID 2956311.1)
Last updated on JUNE 29, 2023
Applies to:
Oracle Advanced Supply Chain Planning - Version 12.2.6 and laterInformation in this document applies to any platform.
Symptoms
There is an end assembly item with a component. This component also has a substitute component defined. The plan is generating a Planned Order for the primary component even though there is currently on hand available for the substitute component.
Assembly
|
Component A > Substitute Component
We expect the plan should use the substitute component which is on hand and available before generating a planned order for the substitute component.
1. Responsibility: Advanced Supply Chain Planner
2. Navigation: Supply Chain Plan > Workbench
3. Query assembly and expand pegging region
4. Observe the missing information
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |