My Oracle Support Banner

Inline Forecast Consumption at Demantra Forecast Level Not Consuming Forward Days (Doc ID 2968529.1)

Last updated on AUGUST 17, 2023

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.2.6 and later
Information in this document applies to any platform.

Symptoms

While running an Advanced Supply Chain Planning plan, it is not performing backwards forecast consumption when a local Demantra forecast is attached and the Forward Days and Backward Days options are set at the Organization level. 

Forward Days are being recognized, but the Backward Days value is not respected.

The expectation is that both Forward Days and Backward Days options should be respected.

The issue can be reproduced at will with the following steps:

  1. (R) Advanced Supply Chain Planner
  2. (N) Supply Chain Plan > Options
  3. Select the desired plan from the list of values
  4. Under the Organizations tab, place the cursor on an organization and then add a local Demantra Forecast
  5. For that Demantra Forecast, scroll to the right and specify values for the Backward Days and Forward Days options
  6. (R) Advanced Supply Chain Planner
  7. (N) Supply Chain Plan > Launch
  8. Specify the parameters for the plan and launch it.

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.