The Assign Activities Window Does Not Display Some Project Activities in Timesheets
(Doc ID 2975818.1)
Last updated on DECEMBER 21, 2023
Applies to:
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 21.12.13.0 to 23.11 [Release 21.12 to 23.11]Primavera P6 Enterprise Project Portfolio Management - Version 21.12.13.0 to 23.12 [Release 21.12 to 23.12]
Information in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
Users cannot assign activities because activities are not present in the list from Team Member.
EXPECTED BEHAVIOR
Users are able to assign activities themselves.
The issue can be reproduced at will with the following steps:
- In Team Member, navigate to Timesheets.
- Click Actions > Assign Activities.
- Search for an Activity with the desired ID #.
- No activities are shown in the list for the relevant project.
Changes
Cause