A Baseline Project Is Not Copied When Copying a Project to a Different EPS Node
(Doc ID 2978261.1)
Last updated on OCTOBER 11, 2023
Applies to:
Primavera P6 Professional Project Management - Version 22.12 to 21.12.7.0 [Release 22.12 to 21.12]Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 23.1 to 23.8 [Release 23.1 to 23.8]
Information in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
When copying a project to a different EPS node, the baseline project is not copied with it.
EXPECTED BEHAVIOR
Baseline projects should be copied when copying a parent project to another EPS node.
The issue can be reproduced at will with the following steps:
- Copy a project (that has one or more baselines) and paste it in a different EPS node.
- Observer that the baseline project(s) are not copied over with the parent project.