Project Calendar's Workweek in Detailed Work Hours/Day Got Changed After Click OK in Total Work Hours/Day. (Doc ID 2993783.1)

Last updated on DECEMBER 20, 2023

Applies to:

Primavera P6 Professional Project Management - Version 20.12.18.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 20.12.18.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
P6 Project Calendar's workweek time period got changed after click OK to save.

EXPECTED BEHAVIOR
-----------------------
Project Calendar workweek time period should be same after click OK.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

  1. Login P6 Client, open a project Calendar, click Modify it.
  2. Once the modify tab is opened, click Detailed Work hours/day and then select "Workweek"
  3. In Workweek, update the working hours from 12PM to 9 PM for example and click OK.
  4. Then go to "Total work hours/day" and click on the Workweek to check on the hours.
  5. So once click OK and return back to Detailed work hours/day tab, can see that the work hours have been modified.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.