Project Calendar's Workweek in Detailed Work Hours/Day Got Changed After Click OK in Total Work Hours/Day.
(Doc ID 2993783.1)
Last updated on DECEMBER 20, 2023
Applies to:
Primavera P6 Professional Project Management - Version 20.12.18.0 and laterPrimavera P6 Enterprise Project Portfolio Management Cloud Service - Version 20.12.18.0 and later
Information in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
---------------
P6 Project Calendar's workweek time period got changed after click OK to save.
EXPECTED BEHAVIOR
-----------------------
Project Calendar workweek time period should be same after click OK.
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
- Login P6 Client, open a project Calendar, click Modify it.
- Once the modify tab is opened, click Detailed Work hours/day and then select "Workweek"
- In Workweek, update the working hours from 12PM to 9 PM for example and click OK.
- Then go to "Total work hours/day" and click on the Workweek to check on the hours.
- So once click OK and return back to Detailed work hours/day tab, can see that the work hours have been modified.
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |