Symptoms

When running an Advanced Supply Chain Planning (ASCP) plan with MPS plan output as input demand schedule, component's Suggested Due Date of MPS planned items is incorrect.

Plan Option "Material Scheduling Method" is set to 'Operation Start Date'.

1. Launch ASCP Plan

Nav: Advanced Supply Chain Planner (R) -> Supply Chain Plan -> Plans -> Select the plan and click launch

2. Review the plan output.

Nav: Advanced Supply Chain Planner (R) -> Supply Chain Plan -> Workbench -> Right Click on Plan -> Supply\Demand-> Supply\Demand -> Query the item -> Review the plan output

Planned order of MPS planned item has the following dates:

Sugg Due Date = 03-SEP-2025 and Sugg Start Date = 15-JUL-2025

However the planned order demand for the component is on 03-SEP-2025.

Expectation is that the planned order demand is generated with due date of 15-JUL-2025.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.