Activity Status Not Showing as Completed When Units % Complete is at 100%
(Doc ID 3046960.1)
Last updated on SEPTEMBER 23, 2024
Applies to:
Primavera P6 Professional Project Management - Version 18.8 and laterInformation in this document applies to any platform.
Goal
Why is the Activity Status not changing from "In Progress" to "Completed" when Units % Complete reaches 100% for the Resources assigned to the Activity?
Solution
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Goal |
Solution |