When Adding Item Relationship to Task, an Additional Item Is Getting Added at the Same Time
(Doc ID 3048807.1)
Last updated on SEPTEMBER 19, 2024
Applies to:
Oracle Agile Product Collaboration - Version 9.3.6.0 and laterInformation in this document applies to any platform.
Symptoms
While adding Item Relationship to task, an additional item is added at the same time
STEPS
The issue can be reproduced at will with the following steps:
1) Open a created task
2) Delete 1 or more rows(items) from Content Tab
3) Actions -> Save as
4) Fill the fields (name, description, Select All Optional Content)
5) Modify Schedule Start End Date, Save it
6) Add button in the Content Tab
7) Write Item name pattern then search
8) Choose one with double click
9) If the issue does not appear go to the first step
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |